Fortis was subcontracted by a client to complete the rope installation phase of a mines production shafts new hoist system install. The first phase of the scope of work for this project was to de-rope the existing balance ropes and head ropes from the Koepe hoist as well as remove the existing 30-ton skips. This was in preparation for the rope-up of the new six rope ground mounted hoist. Once the hoist was de-roped, Fortis then assisted in the removal of the koepe hoist from the headframe. To start the second phase of the project Fortis repositioned the guide ropes and cheeseweights in the shaft to accommodate the new larger 50 ton skips. Balance ropes were installed followed by the installation of the six head ropes. For this project Fortis supplied a 40,000 lbs. winch that served several functions on the project. Fortis is proud to have safely and successfully completed this project.
De-Rope, Rope-Up & Skip Change Out
Service(s) Provided: Mine Hoist Roping & Conveyance Services